Project timeline

  • Presentation of project | 06.09.2018
  • Planning starts | Autumn 2018
  • Release of the preliminary draft | August 2019
  • Neighbours' info event | 11 September 2019
  • Resolution of the zoning in the City Council | January 29, 2020
  • Start of construction | October 2020
  • Start of carcass construction | Beginning of 2022
  • Start of expansion | Mid 2023
  • Completion of construction | Autumn 2024
  • Full university operation | Autumn 2025 - or Winter Semester 2025